Oregon Journeyman Plumber License Exam Exam Prep
Free practice questions

Free OR-JP Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The OR-JP exam has 64 questions and runs 4 hours.

These 10 free OR-JP questions are organized by exam domain, so you can see how each part of the Oregon Journeyman Plumber License Exam blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Understanding of engineering and architectural drawings and plans sufficient to prepare a bill of materials and lay out a plumbing system

Question 1

The valve schedule specifies a bronze ball valve with 3/4-inch female NPT ports at both ends. It will be installed in a 3/4-inch copper line assembled with soldered joints. The material takeoff already includes the valve and tubing. Which addition completes both valve-to-tube connections?

Show answer & explanation

Correct answer: A - Two male-NPT-by-solder adapters.

Question 2

An issued plumbing detail dimensions a pipe leg at 60 inches center-to-center between fittings. On a reduced site copy, the same leg measures 54 inches when read with the original drawing scale. For the fabrication takeoff, which basis should determine the pipe cut length?

Show answer & explanation

Correct answer: A - The 60-inch written dimension, less the effective fitting takeouts.

Domain 2: Ability to compute areas of regular plane figures, volumes of regular solids, slopes, offsets, clearances, and weights of piping

Question 3

Two parallel pipe runs are to be joined by a rolling offset using two 45-degree elbows. Their centerlines are separated by a 12-inch rise and a perpendicular 16-inch roll. Each elbow has an effective takeout of 1.50 inches along the diagonal pipe. What straight-pipe cut length is required between the elbows, to the nearest 0.01 inch?

Show answer & explanation

Correct answer: B - 25.28 inches

Question 4

A 30-foot horizontal drain route must connect an upstream invert at elevation 100.50 feet to an existing downstream invert at 99.75 feet. Both elevations are fixed. The approved design requires a uniform grade of at least 1/4 inch per foot. Does the available fall permit this gravity connection?

Show answer & explanation

Correct answer: C - Yes; 9 inches of fall is available, exceeding the required 7.5 inches.

Domain 3: Selection and use of tools, materials and techniques commonly used in the plumbing trade

Question 5

Several fixtures have weak flow. Test gauges connected immediately before and after a cartridge filter both read 66 psi with no water running. At the same flow used during commissioning, the inlet gauge reads 62 psi and the outlet gauge reads 29 psi; the filter had very little pressure loss when new. Where should the repair effort start?

Show answer & explanation

Correct answer: C - Isolate and service the filter, then repeat the flowing-pressure test.

Domain 4: The Plumbing Specialty Code, administrative rules relating to plumbing and plumbers and general scientific principles covering hydraulics

Question 6

After a water meter with an integral check valve is installed, a home's water pressure is 58 psi while the water heater is idle and climbs to 112 psi during recovery with all fixtures closed. Upstream pressure stays at 58 psi, and the heater's temperature controls operate normally. There is no thermal expansion control. What permanent correction best fits these findings?

Show answer & explanation

Correct answer: C - Install a potable-water expansion tank on the heater's cold supply, downstream of the check valve.

Question 7

A 2-inch sink drain approaches a 3-inch horizontal sanitary branch at a right angle. Both lines remain horizontal at the junction. Which fitting arrangement provides the required directional entry into the branch?

Show answer & explanation

Correct answer: A - A reducing wye and a 45-degree bend, with the wye aimed downstream.

Question 8

A potable-water makeup line serves a process loop containing a toxic corrosion inhibitor. The loop's pump can raise downstream pressure above the supply pressure, and the line remains continuously pressurized. The approved design calls for an in-line backflow prevention assembly. Which assembly matches both the hazard and the pressure conditions?

Show answer & explanation

Correct answer: B - A reduced-pressure-principle backflow prevention assembly.

Domain 5: A general knowledge of construction job safety and occupational safety standards

Question 9

During permitted work in a sewer vault, the entrant becomes unresponsive and the atmospheric monitor alarms. The attendant is trained for the site's non-entry rescue procedure; the entrant's retrieval line is attached and the retrieval path is clear. The attendant is not trained or equipped for entry rescue. Which response puts the rescue plan into effect without creating a second victim?

Show answer & explanation

Correct answer: D - Summon the designated rescue service and begin non-entry retrieval from outside the vault.

Domain 6: A basic understanding of disabled access provisions of the Oregon Structural Specialty Code related to plumbing

Question 10

An adult wheelchair-accessible toilet compartment in a new public restroom contains a floor-mounted water closet. Measurements are taken from finished surfaces. Under the 2010 ADA Standards, which measurement fails its applicable dimensional requirement?

Show answer & explanation

Correct answer: D - Compartment depth: 57 inches from the rear partition.

That's 10 of 1,030

The full bank has 1,020 more OR-JP questions with explanations.

Continue in the free practice test →